16th October 2013
Today we got into our groups and finalised our shot list. We then started on our story board.
17th October 2013
Today we finished our story board and took 'Location Recce' photographs.
18th October 2013
We went out and took some more, improved 'Location Recce' photographs, of all of our chosen locations. We went out to the library to gather more information and to ensure that it was possible to film there; we also completed some more of the Pre-Production paperwork.
22nd October 2013
We completed the risk-assessment paperwork and continued working on our Pre-Production paperwork, including the production schedule.
23rd October 2013
Today we found images of a batman magazine on the internet, and using Photoshop we edited the text to fit in with our end credits.
5th November 2013
We started to film our short clip. The original location had to be changed because of the weather, and so the initial shot has been taken indoors.
6th November 2013
Today we finished filming our short clip. As a result of the weather changing, we were able to shoot some of our footage outside, as originally planned. We then started with the editing process.
7th November 2013
We continued editing our film and aimed to shorten it to the maximum time allowed; 1min 30.
12th November 2013
We continued to edit our clip and change the audio to what was best suited to the actions.
13th November 2013
Today we finished editing our short clip and made sure that our pre-production paperwork was updated onto our individual blog.